Idaho Public
Utilities Commission
Case
No. IPC-E-10-16, -17, -18
July
6, 2010
Contact:
Gene Fadness (208) 334-0339, 890-2712
Website:
www.puc.idaho.gov
Idaho Power agreements with anaerobic
digester projects OK’d
The
Idaho Public Utilities Commission has approved Idaho Power Company requests to
enter into power sales agreements with the developer of three Magic Valley
anaerobic digester power projects.
The
15-year contracts are all with a Middleton-based developer. Two of the projects are in Twin Falls County.
They are the 4-megawatt Rock Creek Dairy project near Filer and the 2-megawatt
Swager Farms Dairy project near Buhl. The 2-megawatt Double B Dairy project is
near Murtaugh in Cassia County.
All
three projects are qualifying facilities under the provisions of PURPA, the
federal Public Utility Regulatory Policies Act of 1978. PURPA requires electric
utilities to offer to buy power produced by qualifying small power producers or
cogenerators. The rate to be paid PURPA project developers, called an “avoided
cost rate,” is determined and published by state commissions. The avoided cost
rate is to be equal to the cost the electric utility avoids if it would have
had to generate the power itself or purchase it from another source.
All
three of the projects contain purchase rates that on the May 24 date of their
contract signing had been replaced by lower rates approved by the commission on
March 16. However, the commission determined that the projects were entitled to
be grandfathered and paid the older, higher rates in place before March
16. An internal review process by Idaho
Power delayed contract signing until May 24 even though all the contract issues
had been resolved before March 16.
For
all three projects, the rate in the first year is $75.65 per megawatt-hour. The
rate gradually increases over the 15 years of the contracts to $128.31 per MWh.
That rate is adjusted for heavy- and light-load seasons as well as heavy- and
light-load hours. The Rock Creek Dairy project intends to deliver 1,296
megawatt-hours per month, while the Swager Farms and Double B project are
anticipating an output of 648 MWh per month.
The commission’s final orders, as well as documents related to these cases, are available on the commission’s Web site at www.puc.idaho.gov. Click on the electric icon, then on "Open Electric Cases” and scroll down to cases IPC-E-10-16, -17 and -18.