FOR IMMEDIATE RELEASE
Idaho Public Utilities Commission
January 13, 2011
Case Nos. IPC-E-10-47, -48, -49, -50,
Order No. 32154
Contact: Gene Fadness (208) 334-0339,
890-2712
Sales agreements with
four wind projects proposed
Idaho Power
Company is asking the Idaho Public Utilities Commission to accept or reject
proposed sales agreements with the developer of four wind farms in the Rogerson
area. The commission is accepting written comment on the sales agreements
through Jan. 31. The developer for all the projects is James Carkulis of
Boise-based Exergy Development.
All four
projects are proposed for acceptance under the provisions of the federal Public
Utilities Regulatory Policies Act, or PURPA.
Idaho Power said it is complying with its PURPA mandate to accept power
generated from qualifying renewable facilities but, at the same time, states that
the “continuing and unchecked requirement” for the company to acquire
additional intermittent generation regardless of the utility’s need for
additional energy “increases the price its customers must pay for their energy
needs.” Idaho Power also stated that the PURPA requirement is circumventing its
planning process and creating system reliability and operational issues.
PURPA
was passed by Congress in 1978 to encourage development of renewable energy
technologies as alternatives to burning fossil fuels or building new power
plants. The act requires that electric utilities offer to buy power produced
from qualifying small-power producers at rates determined by the states. The
rate to be paid small-power developers, called an avoided-cost rate, is to be
equal to the cost the utility avoids if it would have had to generate the power
itself or purchase it from another source.
Last
November, Idaho Power, along with two other regulated electric utilities
operating in Idaho, asked the commission to immediately reduce the size of
projects eligible for posted PURPA rates from the current 10 megawatts or 100
kilowatts. All four of the proposed Rogerson wind projects would deliver up to 10
average megawatts per month under the proposed agreements. However, the
agreements also state that Idaho Power can curtail generation from the projects
without compensation to the developer under certain conditions. Those
conditions include times when generation on Idaho Power’s total system
approaches minimum levels needed to serve customers and further acceptance of
the wind would have a detrimental effect on the utility’s ability to
simultaneously manage the generation also coming from thermal, hydro and other
resources. Idaho Power maintains it now
has 208 MW of wind generation and another 264 MW of approved wind contracts were
scheduled to be online by the end of 2010. The utility claims it could have
1,100 MW of wind generation on its system in the near term, which exceeds the
amount of power used in its total system on the lightest energy-use days.
The rate proposed for the four projects is a
non-levelized rate that increases through the 20-year
life of the contract. The scheduled operation date for the projects is June 30,
2012. In 2012, the agreement’s proposed rate for normal load hours during
normal seasons of the year is $58.68 per megawatt-hour, escalating to $117.77
per MWh in 2031. The rate varies to account for heavy
and light load hours of the day and heavy and light load seasons of the year. The
commission must ensure the avoided-cost rate is reasonable for utility
customers because 100 percent of the price utilities pay to qualifying
producers is included in customer rates.
Comments are accepted through Jan.
31 via e-mail by accessing the commission’s homepage at www.puc.idaho.gov and clicking on
"Comments & Questions About a Case."
Fill in the case number (IPC-E-10-47, -48, -49 and -50) and enter your
comments. Comments can also be mailed to P.O. Box 83720, Boise, ID 83720-0074
or faxed to (208) 334-3762. The company can file reply comments by no later
than Feb. 2.
A full
text of the commission’s order, along with other documents related to this
case, is available on the commission’s Web site at www.puc.idaho.gov. Click on “File Room”
and then on “Electric Cases” and scroll down to the above case number.