Idaho Public Utilities Commission
Case
No. IPC-E-12-02, Order No. 32465
February
24, 2012
Contact:
Gene Fadness (208) 334-0339, 890-2712
Idaho Power proposes settlement with Hoku Industries
The
Idaho Public Utilities Commission is taking comments through March 7 on a
proposed settlement to a Pocatello manufacturing plant’s request to amend its
contract with Idaho Power Company.
Idaho
Power threatened to disconnect service to Hoku Materials, Inc. last December
because production delays caused by market conditions made it difficult for the
polysilicon manufacturer to make a minimum monthly
payment of about $1.8 million. The
minimum monthly payment is not based on electricity consumed – the plant is not
yet in production – but is required to meet expenses Idaho Power incurs to be
ready to meet Hoku’s expected demand up to 82 megawatts.
Both
commission staff and Idaho Power maintain the proposed settlement addresses
Hoku’s cash flow problems while at the same time protecting the utility and its
customers. The proposed agreement
reduces Hoku’s monthly minimum payment to about $800,000 for up to 18 months
through June 2013. To protect customers
and the company from the lost revenue due to the lower minimum payment, the
agreement also proposes to require Hoku to eventually reimburse the difference
between the current and the proposed minimum plus 6 percent interest via
monthly payments through November 2014.
Further, Hoku agrees to make an initial payment of $3.8 million to Idaho
Power, with $2 million of that coming from an existing $4 million deposit
already provided by Hoku. The remaining $1.8 million will be paid over the next
18 months at $100,000 per month. If the
plant is able to increase production it must give Idaho Power 30 days’ notice when
it plans to exceed 10 MW and six-months’ notice when it plans to exceed 20
MW.
These
provisions, the company and commission staff maintain, ensure Idaho Power and
its ratepayers are protected while allowing Hoku time for the polysilicon market to improve. Ratepayers are impacted because Idaho Power included the revenue it was originally
contracted to receive from Hoku in both its 2011 rate case filing and its Power
Cost Adjustment filings. Without the
Hoku revenue, the resulting deficiency would have had to been made up by other
Idaho Power customers. The proposed
settlement ensures that Idaho Power customers are no worse off than they
otherwise would have been had the contract not been amended, according to
commission staff.
The
reduction in Hoku’s minimum monthly payment flows through Idaho Power’s annual
Power Cost Adjustment (PCA) resulting in higher than normal net power supply
expenses, which are passed on to Idaho Power customers. The settlement proposes that the customer
share of the deferred revenue that would have otherwise come from Hoku be
tracked on a monthly basis with a 6 percent carrying charge. That balance will then be reimbursed to
customers over the 12-month period from December 2013 to November 2014.
Hoku, which will manufacture, market and sell polysilicon
to the solar industry, originally said it would be taking energy on June 1,
2009, but then requested an amendment to the contract with a December 1, 2009,
online date. In February 2010, the
commission approved an Idaho Power and Hoku request to amend the contract to
waive payment of the monthly minimum charge until April 1, 2011. Unable to pay its November 2011 bill, Hoku
filed a petition in December asking the commission to protect it from
termination and suspend its monthly minimum payment until an amendment to the
contract is approved. The commission
denied the suspension because it would violate a commission prohibition of
"retroactive ratemaking," which would occur if the commission
stayed collection of rates already under contract. Further, the
commission said, entirely suspending Hoku's payments adversely impacts other
customers. The commission directed Idaho Power and Hoku to immediately
enter into negotiations to reform the contract.
The settlement proposed this week is the result of those
negotiations.
Hoku
did eventually pay its November and December bills.
Idaho Power’s rate schedule requires that large power service
customers whose demand exceeds 20 megawatts make special contract arrangements
with the company. Contracts for large-load customers provide protection to the
company and other retail customers from system impacts that some large loads
could impose because of their sheer size or operating characteristics.
The 2009 contract between Hoku and Idaho Power provides that Hoku
take service under two rate blocks. The first block of energy (all use
over 25 MW) is priced at the commission’s published avoided-cost rate used for
small-power (PURPA) projects. The first
block includes a “take-or-pay” provision, obligating Hoku to pay first block
energy and demand charges regardless of whether it consumes power. The
second block (up to 25 MW) is priced at the traditional embedded cost rate for
Idaho Power’s large special-contract customers.
The
production delays are the result of conditions in the polysilicon
market. The spot market price for
solar-grade polysilicon dropped below $30 per
kilogram in 2011 from about $200 in 2006.
The high demand for polysilicon led to rapid
increases in production and by the second half of 2011, supply began to exceed
demand and prices fell below the industry’s average production costs. According
to Hoku, this is expected to continue for another six months, but then the
market is anticipated to improve for manufacturers. To maintain its operation, Hoku is drawing on
various reserves or loans.
Hoku
claimed that termination of service would have prevented completion of the
plant’s construction, possibly freeze sensitive electronic equipment and
threaten 160 jobs. To date, Hoku has invested more than $600 million in
its Pocatello plant, including paying the cost of transmission and substation
facilities to service the plant. The
conversion of silicon to polysilicon is energy
intensive, accomplished through large electric power reactors. When fully operational, Hoku expects to
generate $35.9 million in revenue for Idaho Power, Hoku claims.
The commission plans to handle this
request in a modified procedure that uses written comments rather than
conducting a hearing. Comments are accepted via e-mail by accessing the
commission’s homepage at www.puc.idaho.gov and
clicking on "Comments & Questions About a
Case." Fill in the case number (IPC-E-12-02) and enter your comments.
Comments can also be mailed to P.O. Box 83720, Boise, ID 83720-0074 or faxed to
(208) 334-3762.
A
full text of the commission’s order, along with other documents related to this
case, is available on the commission’s Web site. Click on “File Room” and then
on “Electric Cases” and scroll down to the above case number.
###