Idaho Public Utilities Commission
Case Nos.
IPC-E-12-20, -22, -23, Order No. 32628
August 31,
2012
Contact:
Gene Fadness (208) 334-0339, 890-2712
PUC adopts Idaho Power,
Exergy settlement
State regulators have adopted a
settlement between Idaho Power and the developer of six proposed wind projects that
allows the projects to be terminated in exchange for Idaho Power returning
letters of credit valued at $3 million to the developer.
Exergy Development Group of Idaho
was under contract to deliver power from the six projects -- four approved in
2005 and two approved in 2011 – but none of the projects met their scheduled operation
dates.
Idaho Power filed a complaint
with the commission in July seeking liquidated damages from the Boise-based
developer. Exergy claimed that factors beyond its control, primarily disputes
with Idaho Power over the interconnection process and transmission service
arrangements, caused the projects to be late. The parties entered into
settlement negotiations and mutually agreed that Idaho Power would not seek
damages if Exergy agreed to terminate the projects.
The commission said both Idaho
and its ratepayers benefit from the settlement.
“In particular, ratepayers avoid paying nearly $600 million in energy
payments over the 20-year terms of the Purchase Power Agreements. From Exergy’s
perspective, it recovers the four Letters of Credit,” the commission said.
Further, termination of the agreements permits Idaho Power to avoid buying a
monthly average of 60 megawatts of electricity that the company claims is not
necessary to meet its service obligations.
Under the federal Public Utility
Regulatory Policies Act (PURPA), Idaho Power must buy from qualifying renewable
energy projects at rates published by the commission. The six projects, each with
an average output of 10 megawatts per month, all qualified for the published
rate before the commission lowered the size of wind and solar projects that can
qualify for the rate from 10 average megawatts to 100 kilowatts.
The two 2005 projects were Notch
Butte Wind Park, located between Twin Falls and Shoshone, and Lava Beds Wind
Park, between Blackfoot and Arco. The original online date for those projects
was May 2007, but that was postponed to September 2010.
The four 2011 projects –
Cottonwood Wind Park, Deep Creek Wind Park, Rogerson Flats Wind Park and Salmon
Creek Wind Park – were all proposed in the Rogerson area and were to have been
operating by June 30 of this year.
###