Idaho Public Utilities
Commission
Case No.
IPC-E-10-56, -57 and -58, Order No. 32664
Case No.
PAC-E-10-08, Order No. 32657
October 15,
2012
Contact:
Gene Fadness (208) 334-0339, 890-2712
Petitions from wind
projects denied by Idaho commission
The
Idaho Public Utilities Commission has declined to modify its June 2011 order
that denied power purchase agreements between three Murphy Flats wind projects and
Idaho Power Company. Earlier last week, the commission denied complaints from
the XRG wind project developers regarding its failed attempt to reach sales
agreements with PacifiCorp.
The
developer of the projects that were to have been built near Murphy said that
two declaratory orders issued by the Federal Energy Regulatory Commission issued
subsequent to the Idaho commission’s order “constitute new facts or information
justifying modification of the (Idaho) commission’s order.”
But
because Murphy Flats did not timely appeal the Idaho commission order, the
commission is prohibited by Idaho code to re-litigate an already decided issue,
the commission said. Parties to
commission orders may file petitions for reconsideration within 21 days after a
commission order and then may appeal to the state Supreme Court. Murphy Flat’s request came more than 14 months
after the reconsideration deadline and 10 months after the FERC order.
“The
commission’s ability to amend an order cannot be used to create a right of
appeal or other remedy lost by a party’s lack of diligence,” the commission
said.
The
FERC order, issued in October 2011, said the commission’s denial of a power
purchase agreement between Idaho Power and the Cedar Creek wind projects in
eastern Idaho were inconsistent with the federal Public Utility Regulatory
Policies Act (PURPA). Because the
circumstances surrounding the Cedar Creek agreement and the Murphy Flats
agreement are similar, Murphy Flats sought a modification of the order that
denied its sales agreements. However, Cedar
Creek petitioned for reconsideration and appealed to the Idaho Supreme Court. Eventually
a modified version of the Cedar Creek sales agreement was approved.
The
commission also denied a complaint by XRG, developer of four wind projects in
Cassia County, against PacifiCorp, which does business as Rocky Mountain Power
in eastern Idaho.
XRG
maintained its yet-to-be-constructed wind projects should have been eligible to
be paid a higher rate by Rocky Mountain Power because it requested a proposed
power purchase agreement with the utility in January 2009, well before the
commission’s March 2010 decrease to the published rate wind developers were
allowed at the time.
Under
PURPA, regulated utilities must buy from qualifying small-power producers at a
rate published by state public utility commissions or negotiated between the
utility and the project. The rate, called an avoided-cost rate, is based on the
cost the utility avoids by not having to generate the power itself or buying it
elsewhere. Idaho’s avoided cost rate is based on the cost to generate power at
a combined-cycle natural gas plant. When the Northwest Power and Conservation
Council issues a new price forecast for wholesale natural gas prices, the
commission adjusts its published avoided cost rate accordingly. In March 2010,
the commission lowered the rate after a council forecast reflected lower
natural gas prices.
Rocky
Mountain Power alleged that transmission in the area XRG was requesting to interconnect
was constrained and XRG did not have the interconnection and wheeling
agreements with Raft River Electric Cooperative and the Bonneville Power
Administration needed to deliver the proposed wind projects’ output to Rocky
Mountain’s territory. XRG said securing
firm transmission and interconnection rights before creating a legally
enforceable power purchase agreement is not a requirement in Idaho. Rocky
Mountain Power claimed that when power must be delivered from off its system
through other entities, some of which are not regulated by the Idaho commission
– such as Raft River Electric – advance agreements are necessary.
XRG
filed a complaint with the commission, alleging that Rocky Mountain Power’s actions
unnecessarily delayed contract signing. The commission agreed to hear oral
arguments.
The
commission ruled that XRG failed to establish that allowing its interconnection
agreement with BPA to lapse was due to bad conduct by Rocky Mountain Power. “XRG made a choice at that time allow its
interconnection request with BPA to lapse because BPA was requiring $80,000 for
an additional interconnection study,” the commission said.
Further,
XRG did not prove it took sufficient steps to ensure it could deliver energy to
Rocky Mountain Power. Communications waned between XRG and Rocky Mountain Power
during 2009 and early 2010, the commission said. “It was not until March 2010,
when XRG received notice of the commission’s intent to revise its published
avoided cost rates that XRG attempted in earnest to establish its entitlement
to contracts.”
XRG
did not file its complaint requesting grandfathered rates to pre-March 2010
rates until July 29, four months after the rate change. Following issuance of its final order, while
the commission was reconsidering the XRG complaint, XRG modified its proposal
asking the commission to approve the post-March 2010 rate if it cannot find in
favor of the earlier higher rate.
“It
is wholly inappropriate and patently unfair for XRG to request an amendment 12
months after its original complaint was filed and more than four months after a
final order has been issued on its complaint,” the commission said.
###