Case Summary
| Last Updated | Case Number | Date Filed | Case Type | Status | Description |
|---|---|---|---|---|---|
| 09/22/2025 | IPC-E-25-29 | 09/19/2025 | Application | Notice Received | IDAHO POWER COMPANY -- APPLICATION FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR THE BENNETT GAS EXPANSION PROJECT AND FOR AN ASSOCIATED ACCOUNTING ORDER |
Case Files
09/19/2025 APPLICATION.PDF
Orders & Notices
10/15/2025 INTERVENTION_ORDER_NO_36804.PDF
10/15/2025 NOTICE_OF_APPLICATION_ORDER_NO_36802.PDF
11/04/2025 INTERVENTION_ORDER_NO_36830.PDF
11/07/2025 NOTICE_OF_PARTIES.PDF
Intervenor
Idaho Irrigation Pumpers Association:
10/02/2025 PETITION TO INTERVENE.PDF
Micron Technology:
10/24/2025 PETITION TO INTERVENE.PDF
Public Comments