Case Summary
| Last Updated | Case Number | Date Filed | Case Type | Status | Description |
|---|---|---|---|---|---|
| 04/09/2026 | IPC-E-26-09 | 04/03/2026 | Application | Notice Received | IDAHO POWER COMPANY -- APPLICATION FOR CERTIFICATES OF PUBLIC CONVENIENCE AND NECESSITY FOR SEGMENT E-8 OF THE GATEWAY WEST 500-kV TRANSMISSION LINE |
Case Files
04/03/2026 APPLICATION - REDACTED.PDF
04/03/2026 DIRECT BARRETTO - REDACTED.PDF
04/03/2026 DIRECT ELLSWORTH.PDF
04/03/2026 DIRECT VAIL.PDF
Orders & Notices
04/20/2026 INTERVENTION_ORDER_NO_37008.PDF
04/20/2026 NOTICE_OF_APPLICATION_ORDER_NO_37010.PDF
05/20/2026 INTERVENTION_ORDER_NO_37045.PDF
05/26/2026 NOTICE_OF_PARTIES.PDF
Company
Intervenor
Idaho Irrigation Pumpers Association:
04/08/2026 PETITION TO INTERVENE.PDF
Micron Technology:
05/11/2026 PETITION TO INTERVENE.PDF
Public Comments